1990
|
|
June
|
Proposition 111 passes increasing the Statewide gas tax and
requiring congestion management programs |
|
1991
|
|
May
|
Joint Powers Agreement becomes effective creating the Alameda
County Congestion Management Agency |
|
October
|
1991 Congestion Management Program approved by CMA Board |
|
1992
|
|
May
|
CMA designated as overall program manager for the TFCA vehicle
registration fee program |
|
August
|
First TFCA vehicle registration fee program approved by CMA Board |
|
November
|
First Bay Area CMA policy-maker conference hosted by Alameda County
CMA |
|
1993
|
|
March
|
Jobs/Housing Balance Issue Paper completed and distributed |
|
October
|
1993 Congestion Management Program and STP/CMAQ
Program approved by CMA Board |
|
1994
|
|
January
|
Pricing Strategies Issue Paper completed and distributed |
|
May
|
Long range Countywide Transportation Plan
(Transportation Vision 2010) approved by CMA Board |
|
Summer
|
Studies initiated in I-580, I-880 and I-80 corridors |
|
1995
|
|
March
|
CMA Becomes member of EDAB |
|
Fall
|
1995 Congestion Management Program approved CMA
sponsors Trip Reduction seminar 1996 State Transportation Improvement Program
list
|
|
December
|
CMA and EDAB establish transportation task force |
|
1996
|
|
January
|
Board holds retreat to discuss future |
|
April
|
CMA Board adopts 1996 federal funding program |
|
1997
|
|
Winter
|
Board retreat relative to Measure B reauthorization 1996
Transportation Per formance Report published CMA Board joins Altamont Commuter
Express JP |
|
April
|
San Pablo Avenue Corridor Study completed |
|
Summer
|
1997 Congestion Management Program adopted |
|
November
|
1997 Transportation Performance Report
approved/Mobility Monitor
|
|
1998
|
|
January
|
Joint ACTA/CMA Board retreat CMA Board adopts 1998 STIP list
|
|
April
|
San Pablo Avenue Corridor Study completed |
|
May
|
1997 Congestion Management Program adopted |
|
August
|
Financial Incentives Program Implemented
1997 Transportation Performance Report approved/Mobility Monitor
|
|
1999
|
|
January
|
CMA adopts Strategy for oversight of projects funded on the STIP |
|
Spring
|
CMA odopts Strategy for accelerated
implementation of I-680 HOV Lane Project |
|
Fall
|
1999 Congestion Management Program Adopted |
|
2000
|
|
May
|
CMA adopts Local Funds Exchange Program |
|
September
|
CMA adopts implementation plan for TCRP Projects |
|
2001
|
|
January
|
I-880 Corridor Strategy Plan adopted |
|
March
|
I-680 Corridor - Phase I Improvements completed |
|
May
|
10th Anniversary of CMA
|