Construction Summary
The CMA continues to work with Caltrans to expedite the delivery of improvements
in the I-680 Corridor. The first phase of the improvements, an auxiliary lane
between Mission Blvd and Automall Parkway was designed and constructed under
the direction of the CMA and was opened to traffic in March of this year. The
second phase of the project, widening of the shoulders for an HOV lane between
Route 84 and Route 237 was completed in 2002. The CMA is currently managing the
construction of soundwalls that have been identified in the environmental
document. Construction of these walls is underway and scheduled to be completed
in the Fall of 2005. Additional project information can be found at the
Caltrans project Hotline: 510-286-5910.
|